Prepared for
Shark Bay Resources Pty Ltd
Useless Loop · Heirisson Prong · Shark Bay, Western Australia
Project
Bitterns Recycling — Field Piping Installation
SOW 7.9 & CONTRACT cl. 9.3
Reporting
Templates
| Document number | DTL-PRJ0072-RPT-001 |
| Contains | Daily pre-start · Weekly report · Monthly / fortnightly progress report |
| Date | 16 July 2026 |
| Requirement | SOW 7.9 (daily & weekly) · Contract cl. 9.3(a) (monthly → fortnightly) |
Cadence. The progress report is
monthly, switching to FORTNIGHTLY from 20 August 2026 (three months before Completion) per cl. 9.3(a).
DTL (WA) Pty Ltd · 2/28 Horus Bend, Bibra Lake WA 6163 · ABN 45 677 646 454 · Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 1 of 4
Reporting TemplatesBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-RPT-001
Rev A
1Daily pre-start (SOW 7.9)
Documented daily and forwarded to the SBR representative.
| Date | |
| Supervisor | |
| Crew on site | |
| Weather / conditions | |
Work planned today
Key hazards & controls / permits in force
SWMS / JSA / Take 5 completed
Interfaces today (SBR electricians, civil, haul roads)
Toolbox talk topic
2Weekly report (SOW 7.9)
Works carried out this week (and cumulative)
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 2 of 4
Reporting TemplatesBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-RPT-001
Rev A
Works planned next week
Issues & delays
Technical queries (TQ / RFI) raised & status
EH&S issues & statistics (incidents, near-misses, spills, hours)
Resources on site (personnel, plant, diesel usage)
Progress vs programme — % complete
Discussed at the weekly progress meeting with SBR stakeholders (SOW 7.9): actual vs planned
progress, next week’s plan, HSE concerns, and any other issues.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 3 of 4
Reporting TemplatesBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-RPT-001
Rev A
3Monthly / fortnightly progress report (cl. 9.3(a))
Monthly, switching to fortnightly from 20 Aug 2026. Separate from the weekly report.
| Period | |
| Report no. | |
| Cadence | Monthly / Fortnightly (from 20 Aug 2026) |
Executive summary — status against Completion (20 Nov 2026)
Programme update — critical-path changes (ATTACH the updated Gantt)
Delays & the measures taken to hold the schedule
Progress by work area (% complete vs planned)
HSE & quality summary (incidents, NCRs, audits)
Variations & commercial status
Look-ahead & risks
Attach the updated programme (Gantt). Clause 9.3(a) requires this report to include
an updated programme (timing chart) showing the critical path, delays, and the measures taken to hold
the schedule. Produce it in your scheduling tool and attach it — this page is the written summary that
accompanies it.